AES Tisza Reconstruction of the control system II. power plant, 1-4. block control system implementation plan 2002 to 2004 Control Engineering | AJKA GT Gas turbine (2×58 MW) installation project power system and control system implementation plan mechanical design of the air technology 2009 to 2011 Gas turbine installation and improvement of the oil storing system power system and control system implementation plan 2012 Control Engineering Power Engineering |
Chinoin Zrt. Site in Tó Street, I. chemical plant THAN manufacturing: control system implementation plan 2002 to 2006 Control Engineering | Craiova II. Power plant Dense slurry system creating the control system’s plan creating Ovation (developed by Emerson) user’s software 2008 to 2009 Control Engineering |
Daimler-Mercedes Daimler-Mercedes automotive factory power supply Kecskemét power system and control system implementation plan 2010 to 2012 Control Engineering Power Engineering | Dél-Nyírség Power Plant Cooling system power system and control system implementation plan 2008 to 2013 Control Engineering Power Engineering |
Dorogi Fűtőerőmű Kft. Converting the 5th boiler for using oil burner 1996 Control Engineering | Duna-Dráva Cement Factory Power supply dry mortar factory (Vác) power system implementation plan 1997 Power Engineering |
Dunaferr Co., Acélművek Ltd. Continuous furnace implementation plan of a continuous furnace programming for Siemens S-7 (STEP7) 1997 to 1998 Reconstruction of boiler IX. power system and control system implementation plan 1999 to 2000 Control Engineering Power Engineering | Dunamenti Power Plant G3 block switchgear power system implementation plan 2009 Power Engineering |
Dunaújváros, Verebélyi Street Power Plant Gas motor power plant power engineering 2004 Power Engineering | Estonia Water cleaning equipments power system and control system implementation plans 1998 to 2001 Control Engineering Power Engineering |
Főtáv Co. Heating Plant in Újpalota Control Engineering Power Engineering | Heating Power Plant in Győr Boiler No. 5 software modification 1995 to 1996 Boiler KVGM-100 power system and control system implementation plan 1998 to 1999 Power Engineering |
Heating Power Plant in Kazincbarcika New gas-based heat sourse (gas motor) power system implementation plan 2001 to 2002 Power Engineering | Heating Power Plant in Tiszaújváros New gas-based heat source (gas motor) power system implementation plan 2001 to 2002 Power Engineering |
Heating Power Plant in Várpalota New gas-based heat source (gas motor) power system implementation plan 1998 to 1999 Power Engineering |
Hosszúrét subdivision Gas motor power plant power engineering 2004 to 2005 Power Engineering |
Hungrana Ltd. Improvements in Szabadegyháza (fructose plant, dextrose plant, alcohol plant, sugar plant) power system and control system implementation plan creating ABB (Freelance 2000) software and its improvement creating Yokogawa software (Centum CS3000) 1997 to 2006 Control Engineering Power Engineering |
Isalnita Power Plant Dense slurry sytem control system plan creation of Ovation user’s software (developed by Emerson) 2009 Control Engineering |
Jacksonville Dense slurry system hardvare plans for the control system 2001 Control Engineering |
MÁV Nosztalgia Ltd. Gas motor power plant power engineering 2004 Power Engineering |
Miskolci Hőszolgáltató Ltd. New gas-based heat source (gas motor) control system implementation plan mechanical design of air technology 2002 to 2003 Control Engineering |
MOL Nyrt. Szank software creation (H&B Freelance) 1996 to 1999 PLC/DCS programming |
MVM Co., MAVIR Co. Air conditioning system power system implementation plan 1996 to 1999 Power Engineering |
North-Buda Heating Power Plant Installation of gas turbines power system and control system implementation plan mechanical design of the air technology 2006 to 2007 Control Engineering Power Engineering |
Pannon Power Co., Power Plant in Pécs Biomass reconstruction power system and control system implementation plan 2003 to 2004 Oil and natural gas reconstruction boiler nr. 5-7 power system and control system implementation plan 2003 to 2004 Control Engineering Power Engineering |
Power Plant in Kőbánya Control Engineering |
Power Plant in Lőrinci Gas turbine block heat utilizer boiler and supplementary equipments tender plan and implementation plan 1997 to 1999 |
Power Plant in Nyíregyháza Control equipment boilers Nr. 9 and 10 software creation (ABB, Freelance 2000) 2004 to 2006 PLC/DCS Programming |
Power Plant in Turcen Dense slurry system control system implementation plan Ovation (developed by Emerson) user’s software creation 2010 to 2012 Control Engineering |
Richter Gedeon Nyrt. Air handling and air conditioning system power system implementation plans York PLC (YES) software creation and putting into operation 1996 to 2003 Tank park established on the site of Richter Gedeon Co. control system implementation plan Emerson (Delta V) software creation 2002 to 2006 Control Engineering Power Engineering |
Rovinari Power Plant Dense slurry system control system implementation plan Ovation (developed by Emerson) user’s software creation 2008 to 2009 | Szegedi Vízmű Co. Wastewater plant reconstruction in Szeged power system and control system implementation plan 2005 to 2006 Control Engineering Power Engineering |
Székesfehérvár Gas motor power plant Power system implementation plans 2005 Power Engineering | Tatabányai Erőmű Ltd. PC-ÜSR and 115-H program software modification 1996 Gas motor installation site of Tatabányai Erőmű Ltd. control system implementation plan 2004 Control Engineering |
Tesco Budaörs Installation of cooling system for the Climasol system PLC improvement: planning, software creation, construction 2008 to 2009 | Tessenderlo Chemie drawing of 35.000 schematic diagram by EPLAN 21 program 1999 to 2001 |
TVK Co. Reconstruction and improvement of the tank park’s dewatering system power engineering control system planning 2008 Control Engineering Power Engineering | Vegetable oil extruder, oil manufacturing plant and silo in Foktő contros system implementation plan 2009 to 2012 Control Engineering PLC/DCS programming |
Vértesi Erőmű Co. Level control of the feedwater heater’s tank Power Plant in Oroszlány 1-4. block power system and control system implementation plan 2001 to 2006 Control Engineering Power Engineering | ZuglóTherm Gas motor power station on the Füredi Street control system implementation plan creation of Yokogawa software and putting it into operation 2005 to 2006 Control Engineering |